PERMIT APPLICATION COMMON
Where on your property are you working?:
develop accessible route from Azalea Way (Rhododendron Garden) to the existing gazebo below the Pacific Connections Garden Meadow.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Institutional
Project Value:
750000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
04/22/2026
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
750000
Total Intake Value:
750000
Total Issued Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2021 SBC
Action Type:
Add/Alt
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
SPECIAL PROGRAMS
Is the project an earthquake retrofit of an unreinforced masonry building?:
No