PERMIT APPLICATION COMMON
Where on your property are you working?:
We are working on the second floor of the existing school building, and the second floor of the Pavilion. Total area of work for these two zones is 1726 sf.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Institutional
Project Value:
43000
PERMIT TRACKING COMMON
Review Level:
Field
Application Completed Date:
02/13/2026
Permit Issued Date:
02/16/2026
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
43000
Total Intake Value:
43000
Issue Value: New:
0
Issue Value: Alteration:
43000
Total Issued Value:
43000
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2021 SEBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
Add/Alt
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Educational
Existing Occupancy:
E Classroom - 12th Grade & Below
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Are there residential (non-commercial) tenants/renters currently living in the property? :
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Partial Fire Protection System:
Yes
Fire Alarm:
Yes
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
N/A
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
N/A
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes