PERMIT APPLICATION COMMON
Where on your property are you working?:
Parking Lot
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Industrial
Project Value:
32000
LARGE PUBLIC PROJECTS
Is this a Light Rail Temporary Use for Construction application?:
No
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
02/18/2026
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
32000
Total Intake Value:
32000
Issue Value: New:
0
Issue Value: Alteration:
32000
Total Issued Value:
32000
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2021 SEBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
Add/Alt
Number of Existing Building Stories:
1
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
1
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Assembly
Existing Occupancy:
A-3 Library
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
24
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
2
# of Proposed Onsite Parking:
24
# of Proposed Offsite Parking:
0
# of Proposed Accessible Parking:
3
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Are there residential (non-commercial) tenants/renters currently living in the property? :
No
WASTE DIVERSION
Waste Diversion Plan Required:
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
Yes
Partial Fire Protection System:
No
Fire Alarm:
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Commercial
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Describe any other mechanical systems to be installed as part of this project.:
Outdoor electric vehicle (EV) charging infrastructure: Installation of two (2) Level 2 EV charging stations (FLO single-port pedestals) with associated 208/240V 40-amp dedicated branch circuits, conduits, and concrete pads in existing asphalt parking area. No new HVAC, ventilation, or indoor mechanical systems proposed.