PERMIT APPLICATION COMMON
Where on your property are you working?:
Onsite
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
1110000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
07/02/2025
Permit Issued Date:
01/29/2026
Permit Remarks:
ADDRESS ASSIGNED: TH1)16A TH2)16B SFR2)18A SFR1)18B W DRAVUS ST
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
694000
Intake Value: Alteration:
0
Total Intake Value:
694000
Issue Value: New:
559862
Issue Value: Alteration:
0
Total Issued Value:
559862
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2021 SBC
Action Type:
New
Number of Proposed Building Stories:
4
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Proposed Onsite Parking:
3
WASTE DIVERSION
Waste Diversion Plan Required:
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
Yes
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Total UA Alternative
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Related New Construction Project:
7073534
Temporary Dewatering for Construction:
No
Pipe Lining in the Right-of-Way:
Yes
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Discharge Point Other Type:
(W Dravus St)
Total Disturbed Area:
3505
New Impervious Surface:
1183
New Plus Replaced Impervious Surface:
1590
Total Volume Managed by On-Site Stormwater Management (gallons):
39375
Total Area Requiring Soil Amendment:
732
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
4
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
GREENDL842LL
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
No