PERMIT APPLICATION COMMON
Where on your property are you working?:
Harbor Island, Terminal 18, along the East Waterway
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Industrial
Project Value:
80000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
06/17/2025
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
11009334
Total Intake Value:
11009334
Issue Value: New:
71973
Issue Value: Alteration:
10937361
Total Issued Value:
11009334
BUILDING CODE INFO
What building code was used for your design?:
2021 SBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
Add/Alt
Number of Proposed Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Are there residential (non-commercial) tenants/renters currently living in the property? :
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
N/A
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Special Hazards
Energy Storage System:
Yes
SIDE SEWER INFORMATION
Related New Construction Project:
7046509
DRAINAGE INFORMATION
Drainage Type of Work:
Addition/Alteration
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
4401
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
4401
Total Volume Managed by On-Site Stormwater Management (gallons):
31805
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Sanitary Type of Work:
None
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No