PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
600000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
10/22/2024
Permit Issued Date:
03/18/2025
Inspections Completed Date:
02/26/2026
Permit Remarks:
2 family dwelling
Assigned Addresses: SFR)14308 AADU)1408B ROSLYN PL N
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
537563
Intake Value: Alteration:
0
Total Intake Value:
537563
Issue Value: New:
537563
Issue Value: Alteration:
0
Total Issued Value:
537563
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
10' curb cut on Roslyn Pl N
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
2
# of Proposed Offsite Parking:
0
Offsite Parking Location:
n/a
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
WASTE DIVERSION
Waste Diversion Plan Required:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Related New Construction Project:
7034013
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
Infiltration
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
On Site
Total Disturbed Area:
5454
New Impervious Surface:
2873
New Plus Replaced Impervious Surface:
4058
Total Volume Managed by On-Site Stormwater Management (gallons):
68051
Total Area Requiring Soil Amendment:
841
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Dwelling Units:
3
Reuse Existing Side Sewer System:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
UNITESL836P7
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
No