PERMIT APPLICATION COMMON
Where on your property are you working?:
Onsite
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
600000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
03/11/2024
Permit Issued Date:
07/19/2024
Inspections Completed Date:
07/31/2025
Permit Remarks:
4/11/24 JCB: Assigned address (AADU) 5429B 25TH AVE SW
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
530374
Intake Value: Alteration:
0
Total Intake Value:
530374
Issue Value: New:
530374
Issue Value: Alteration:
0
Total Issued Value:
530374
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
1
# of Proposed Onsite Parking:
3
Tenant Relocation Assistance
Are there residential (non-commercial) tenants/renters currently living in the property? :
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Related New Construction Project:
7006066
Temporary Dewatering for Construction:
No
Pipe Lining in the Right-of-Way:
Yes
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Discharge Point Other Type:
(25th Ave SW)
Total Disturbed Area:
4800
New Impervious Surface:
1709
New Plus Replaced Impervious Surface:
1643
Total Volume Managed by On-Site Stormwater Management (gallons):
51033
Total Area Requiring Soil Amendment:
1448
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
2
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes