PERMIT APPLICATION COMMON
Where on your property are you working?:
The proposed construction will encompass the majority of the property. See preliminary site plan. The single family residence will be towards the front setback from NE 117th St and the DADU will be in the current location of the detached garage structure, the northwest corner of the property.
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
650000
PERMIT TRACKING COMMON
Review Level:
Dependent Building
Application Completed Date:
12/28/2023
Permit Issued Date:
04/10/2024
Inspections Completed Date:
04/24/2025
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
180695
Intake Value: Alteration:
0
Total Intake Value:
180695
Issue Value: New:
180695
Issue Value: Alteration:
0
Total Issued Value:
180695
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2018 SRC
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
New
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
No existing curb on NE 117th St
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units Unoccupied
Are there residential (non-commercial) tenants/renters currently living in the property? :
No
Will the scope of the proposed project displace the tenants/renters?:
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
Central heat pump with ducts and heat pump water heater.
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes