PERMIT APPLICATION COMMON
Where on your property are you working?:
The proposed project area is primarily located within the SDOT ROW but there will be parts of the discussed GSI facility located within the north east side of the parcel in question, while overland piping and its associated connections will be done within the north west corner of the parcel.
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Vacant Land
Project Value:
1400000.00
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
08/27/2024
Permit Issued Date:
02/13/2025
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
350000
Intake Value: Alteration:
0
Total Intake Value:
350000
Issue Value: New:
350000
Issue Value: Alteration:
0
Total Issued Value:
350000
BUILDING CODE INFO
What building code was used for your design?:
2021 SBC (Struct) and SRC (Arch)
Action Type:
Add/Alt
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Offsite Parking Location:
0
# of Proposed Accessible Parking:
0
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes