PERMIT APPLICATION COMMON
Where on your property are you working?:
Work will be conducted through-out property area - from east to west and from alley @ south up to street @ north
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Vacant Land
Project Value:
1170000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
05/07/2025
Permit Issued Date:
01/14/2026
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
1170000
Intake Value: Alteration:
0
Total Intake Value:
1170000
Issue Value: New:
1170000
Issue Value: Alteration:
0
Total Issued Value:
1170000
BUILDING CODE INFO
What building code was used for your design?:
2021 SBC
Action Type:
Add/Alt
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
SIDE SEWER INFORMATION
Related New Construction Project:
6996588
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Alley
Total Disturbed Area:
11197
New Impervious Surface:
3358
New Plus Replaced Impervious Surface:
3358
Total Volume Managed by On-Site Stormwater Management (gallons):
20321
Total Area Requiring Soil Amendment:
7839
SANITARY INFORMATION
Sanitary Type of Work:
None
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes