PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
250000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
03/14/2023
Permit Issued Date:
05/01/2023
Inspections Completed Date:
03/20/2024
Permit Remarks:
04/24/2023 RABB CHANGED ADDRESS FROM: 1014; TO: 1016 NE 98TH ST
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
199753
Intake Value: Alteration:
0
Total Intake Value:
199753
Issue Value: New:
189289
Issue Value: Alteration:
0
Total Issued Value:
189289
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
No
Action Type:
Add/Alt
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
1
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
Are there residential (non-commercial) tenants/renters currently living in the property? :
Yes
Will the scope of the proposed project displace the tenants/renters?:
No
WASTE DIVERSION
Waste Diversion Plan Required:
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Cooling Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Related New Construction Project:
6940180
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
On Site
Total Disturbed Area:
1966
New Impervious Surface:
1018
New Plus Replaced Impervious Surface:
1018
Total Volume Managed by On-Site Stormwater Management (gallons):
16985
Total Area Requiring Soil Amendment:
948
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
1
Number of New Dwelling Units:
1
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
REALPPF855N5