PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
12/01/2022
Permit Issued Date:
05/18/2023
Inspections Completed Date:
05/26/2023
Certificate of Occupancy Issued Date:
05/26/2023
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
0
Total Intake Value:
0
Issue Value: New:
0
Issue Value: Alteration:
0
Total Issued Value:
0
Total Revision Value:
0
PERMIT APPLICATION COMMON
Where on your property are you working?:
The application is associated with the current parking count only with a desire to reduce the number of total stalls. A land use only building permit has been provided by SDCI to the applicant as the best means for permitting this request.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
0
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
431
# of Existing Offsite Parking:
300
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
431
# of Proposed Offsite Parking:
100
Offsite Parking Location:
Seattle Center parking garage
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Basement
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
BUILDING CODE INFO
What building code was used for your design?:
2018 SEBC
Specific Building Code:
SEBC Prescriptive
Action Type:
Change of Use Only - No Construction
Will you change the building use or occupancy?:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes