PERMIT APPLICATION COMMON
Where on your property are you working?:
Substsation T30 is located on the East margin of the property adjacent East Marginal way. It is enclosed by locked fences that require contact with the port authority to access.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Industrial
Project Value:
3000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
08/10/2022
Permit Issued Date:
01/18/2024
Inspections Completed Date:
12/11/2025
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
3000000
Total Intake Value:
3000000
Issue Value: New:
0
Issue Value: Alteration:
3000000
Total Issued Value:
3000000
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC
Is this a substantial alteration?:
Yes
Are you changing the envelope?:
No
Action Type:
Add/Alt
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
1
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Utility and Miscellaneous
Existing Occupancy:
Fence > 6 Ft
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Offsite Parking Location:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
FIRE PROTECTION SYSTEMS
Fire Alarm:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Commercial
Compliance Path:
Component Performance
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
L & I approved.
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Electric Heat Pump
Cooling Fuel Type Proposed: Non-Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Related New Construction Project:
6907880
DRAINAGE INFORMATION
Drainage Type of Work:
None
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
1071
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
1071
Total Volume Managed by On-Site Stormwater Management (gallons):
0
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Sanitary Type of Work:
None
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
DUTTOEC137P3