PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
400000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
07/01/2022
Permit Issued Date:
01/03/2023
Inspections Completed Date:
05/19/2023
Permit Remarks:
08/09/2022 RABB ADDRESSED AADU AS: 4430B 47TH AVE SW
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
193811
Total Intake Value:
193811
Issue Value: New:
0
Issue Value: Alteration:
193811
Total Issued Value:
193811
BUILDING CODE INFO
What building code was used for your design?:
2018 SRC
Is this a substantial alteration?:
Yes
Action Type:
Add/Alt
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
Access to parking provided from alley.
PARKING
# of Proposed Onsite Parking:
3
# of Proposed Offsite Parking:
0
Offsite Parking Location:
NA
# of Proposed Accessible Parking:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Weep Hole
Total Disturbed Area:
5676
New Impervious Surface:
1149
New Plus Replaced Impervious Surface:
2305
Total Volume Managed by On-Site Stormwater Management (gallons):
31726
Total Area Requiring Soil Amendment:
2115
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
3
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
NEWIMI*856PB