PERMIT APPLICATION COMMON
Where on your property are you working?:
Southern and eastern portions of the site with some incidental work on the norther portion of the site between the play field and the existing school.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Institutional
Project Value:
2100000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
10/25/2023
Permit Issued Date:
05/22/2024
Inspections Completed Date:
02/03/2025
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
2100000
Total Intake Value:
2100000
Issue Value: New:
0
Issue Value: Alteration:
2100000
Total Issued Value:
2100000
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC
Action Type:
Add/Alt
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
DRAINAGE INFORMATION
Drainage Type of Work:
Addition/Alteration
Number of Other New Drainage Connections:
1
Flow Control Type:
Pipe
Flow Control Standard:
Pasture and Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
75210
New Impervious Surface:
24197
New Plus Replaced Impervious Surface:
24197
Total Volume Managed by On-Site Stormwater Management (gallons):
4720
Total Area Requiring Soil Amendment:
51013
SANITARY INFORMATION
Sanitary Type of Work:
None
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
DIVEREW804NU