PERMIT APPLICATION COMMON
Where on your property are you working?:
Suite 103, NE corner ground level
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
100000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
06/27/2022
Permit Issued Date:
10/11/2022
Inspections Completed Date:
02/10/2023
Certificate of Occupancy Issued Date:
02/10/2023
Permit Remarks:
C of O needed to establish B occupancy at ground level
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
100000
Total Intake Value:
100000
Issue Value: New:
0
Issue Value: Alteration:
100000
Total Issued Value:
100000
BUILDING CODE INFO
What building code was used for your design?:
2018 SEBC
Specific Building Code:
SEBC Prescriptive
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
Add/Alt
Number of Existing Building Stories:
5
Number of Existing Below-Grade Building Stories:
1
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Main Existing Use of Building:
Assembly
Existing Occupancy:
A-2 Restaurant
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
No parking required under this application; no changes to existing parking proposed.
PARKING
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Offsite Parking Location:
0
# of Proposed Accessible Parking:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
COASTCL850RC