Where on your property are you working?:
Portions of east and west exterior foundations.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
36000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
07/15/2022
Permit Issued Date:
08/16/2022
Inspections Completed Date:
10/12/2022
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
36000
Total Intake Value:
36000
Issue Value: New:
0
Issue Value: Alteration:
36000
Total Issued Value:
36000
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
Add/Alt
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
All Residential Units Occupied by Property Owner
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
SIDE SEWER INFORMATION
Side Sewer Conflict:
Yes
Side Sewer Conflict Description:
The helical piles near the garage may be in conflict with the existing side sewers. Verify in field and protect or reroute side sewer. Side Sewer Card #3726-1
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
RAMJAW*852PW