PERMIT APPLICATION COMMON
Where on your property are you working?:
The entire site
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Commercial
Project Value:
20000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
09/22/2022
Permit Issued Date:
02/22/2023
Inspections Completed Date:
04/05/2024
Certificate of Occupancy Issued Date:
04/05/2024
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
9155104
Intake Value: Alteration:
0
Total Intake Value:
9155104
Issue Value: New:
9155104
Issue Value: Alteration:
0
Total Issued Value:
9155104
INTERDEPARTMENTAL COORDINATION
SDOT Concept Approval:
Yes
SDOT SIP PM:
KT
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
New
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
1
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Main Existing Use of Building:
Storage
Existing Occupancy:
S-1 Storage - Moderate Hazard
Will your application include a new standard plan?:
No
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Piles
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
2
Curb Cut Size and Location:
not yet known. Likely one off 16th & one off 17th/Thorndyke
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
27
# of Proposed Offsite Parking:
0
# of Proposed Accessible Parking:
4
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
9
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any ground-mounted exterior equipment?:
No
Is there any wall-mounted exterior equipment?:
No
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Commercial
Compliance Path:
Component Performance
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
Traditional VRF HVAC
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Electric Heat Pump
Cooling Fuel Type Proposed: Non-Residential:
Electric Heat Pump
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
Pipe
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
50846
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
45492
Total Volume Managed by On-Site Stormwater Management (gallons):
246335
Total Area Requiring Soil Amendment:
5354
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
0
Reuse Existing Side Sewer System:
No
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
SELLEC*372N0