PERMIT APPLICATION COMMON
Where on your property are you working?:
Most of the proposed work is to happen within the footprint of the existing home as a second story addition. We are also proposing slight expansions of the building's existing envelope at the front facing elevation of the home as well as the south facing elevation.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
400000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
02/23/2022
Permit Issued Date:
06/02/2022
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
206720
Intake Value: Alteration:
193280
Total Intake Value:
400000
Issue Value: New:
194735
Issue Value: Alteration:
162086
Total Issued Value:
356821
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
Yes
Are you changing the envelope?:
Yes
Action Type:
Add/Alt
Number of Existing Building Stories:
1
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
1
Number of Proposed Below-Grade Building Stories:
2
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
All Residential Units Occupied by Property Owner
FIRE PROTECTION SYSTEMS
Fire Alarm:
No
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Data Center Building?:
No
Power is Sub-Metered?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
MOUNTBR923MG