PERMIT APPLICATION COMMON
Where on your property are you working?:
Pier 66 - overwater along pier and waterward to the southwest, curving to the southeast.
Terminal 46 - upland work is along the east margin of the property, extending to the northern margin and turning east to west, and then waterward to the northwest toward Pier 66.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Industrial
Project Value:
15000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
03/18/2022
Permit Issued Date:
05/02/2023
Inspections Completed Date:
10/18/2024
Permit Remarks:
No work to occur prior to obtaining all necessary permits from other agencies.
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
15000000
Intake Value: Alteration:
0
Total Intake Value:
15000000
Issue Value: New:
0
Issue Value: Alteration:
15000000
Total Issued Value:
15000000
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC
Action Type:
Add/Alt
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Authorized Government Representative
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes