PERMIT APPLICATION COMMON
Where on your property are you working?:
Entire Site
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
868122
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
06/09/2021
Permit Issued Date:
04/20/2022
Inspections Completed Date:
11/22/2023
Permit Remarks:
11/5/2021, BH, Assigned address for DADU: 919 20TH AVE
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
352749
Intake Value: Alteration:
0
Total Intake Value:
352749
Issue Value: New:
396910
Issue Value: Alteration:
0
Total Issued Value:
396910
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
New
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
10' wide new proposed curb cut located 6' South of the North Property Line.
PARKING
# of Existing Onsite Parking:
2
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
1
# of Proposed Offsite Parking:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
All Residential Units Occupied by Property Owner
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
Data Center Building?:
No
Power is Sub-Metered?:
No
SIDE SEWER INFORMATION
Related New Construction Project:
6835160
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
4840
New Impervious Surface:
729
New Plus Replaced Impervious Surface:
2180
Total Volume Managed by On-Site Stormwater Management (gallons):
29414
Total Area Requiring Soil Amendment:
2060
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
1
Reuse Existing Side Sewer System:
Yes
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes