PERMIT APPLICATION COMMON
Where on your property are you working?:
Roof Parapet, exterior enclosure
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
100000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
01/20/2022
Permit Issued Date:
12/06/2022
Inspections Completed Date:
12/09/2025
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
100000
Total Intake Value:
100000
Issue Value: New:
0
Issue Value: Alteration:
100000
Total Issued Value:
100000
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2018 SEBC
Specific Building Code:
SEBC Prescriptive
Is this a substantial alteration?:
No
Are you changing the envelope?:
Yes
Action Type:
Add/Alt
Is this a high-rise?:
Yes
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-2 Apartment/Condominium
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
N/A
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
Elevator Pressurization:
No
Stairway Pressurization:
No
Smoke Removal System:
No
Accessible Elevator Egress:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
TECHNWI994LO
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
No