PERMIT APPLICATION COMMON
Where on your property are you working?:
Proposed development will encompass entire lot
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
800000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
03/01/2021
Permit Issued Date:
10/01/2021
Inspections Completed Date:
10/06/2022
Permit Remarks:
4/20/23 JCB: Assigned Address for AADU)3043B DADU) 3045 NW 65TH ST
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
594731
Intake Value: Alteration:
0
Total Intake Value:
594731
Issue Value: New:
594731
Issue Value: Alteration:
0
Total Issued Value:
594731
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
2
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
10' curb cut - existing curb cut to be replaced
PARKING
# of Existing Onsite Parking:
2
# of Proposed Onsite Parking:
2
Tenant Relocation Assistance
Residential Unit Occupancy:
All Residential Units Occupied by Property Owner
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
Data Center Building?:
No
Power is Sub-Metered?:
No
SIDE SEWER INFORMATION
Related New Construction Project:
6815910
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
4802
New Impervious Surface:
863
New Plus Replaced Impervious Surface:
1885
Total Volume Managed by On-Site Stormwater Management (gallons):
42634
Total Area Requiring Soil Amendment:
2054
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
3
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
KOHARBL880N2