PERMIT APPLICATION COMMON
Where on your property are you working?:
9314 Renton Ave. S
Seattle, WA 98118
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
10000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
01/16/2021
Permit Issued Date:
04/12/2021
Inspections Completed Date:
02/09/2022
Permit Remarks:
Building permit issuance is required prior to final inspection for this demolition permit; or all disturbed areas shall be fully stabilized, and side sewers shall be capped.
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
GROUND DISTURBANCE
Is the ground disturbance in an environmentally critical area?:
No
New and Replaced Hard Surface > 750 sq ft?:
No
What is the amount of ground disturbance?:
No
DEMOLITION INFO
Type of Demolition:
Demolition
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes