PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
1000000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
06/23/2021
Permit Issued Date:
02/16/2022
Inspections Completed Date:
08/04/2025
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
470735
Intake Value: Alteration:
0
Total Intake Value:
470735
Issue Value: New:
470735
Issue Value: Alteration:
0
Total Issued Value:
470735
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Basement
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
10 curb cut with flares on each side.
PARKING
# of Proposed Onsite Parking:
1
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units Unoccupied
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
Data Center Building?:
No
Power is Sub-Metered?:
No
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Other
Discharge Point Other Type:
W Kinnear PL
Total Disturbed Area:
6392
New Impervious Surface:
3678
New Plus Replaced Impervious Surface:
3678
Total Volume Managed by On-Site Stormwater Management (gallons):
26613
Total Area Requiring Soil Amendment:
2714
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
2
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
JOSEPMC827K3