PERMIT APPLICATION COMMON
Where on your property are you working?:
On the entire site
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
6000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
10/07/2020
Permit Issued Date:
06/14/2022
CONSTRUCTION VALUATION INFO
Intake Value: New:
2340296
Intake Value: Alteration:
0
Total Intake Value:
2340296
Issue Value: New:
2340296
Issue Value: Alteration:
0
Total Issued Value:
2340296
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
New
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
6
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
1
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-2 Apartment/Condominium
Will your application include a new standard plan?:
No
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
N/A
PARKING
# of Existing Onsite Parking:
4
# of Existing Offsite Parking:
0
# of Proposed Onsite Parking:
3
# of Proposed Offsite Parking:
0
Offsite Parking Location:
N/A
# of Proposed Accessible Parking:
1
# of Proposed Bicycle Parking Spots:
13
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units Unoccupied
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any ground-mounted exterior equipment?:
No
Is there any wall-mounted exterior equipment?:
No
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Residential
Compliance Path:
Total UA Alternative
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
HRVs and ductless heat pumps
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Cooling Fuel Type Proposed: Residential:
Electric Heat Pump
Special Requirements:
DR 20-2017 PHIUS passive house.
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
2
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Weep Hole
Total Disturbed Area:
4707
New Impervious Surface:
300
New Plus Replaced Impervious Surface:
4611
Total Volume Managed by On-Site Stormwater Management (gallons):
20448
Total Area Requiring Soil Amendment:
96
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Reuse Existing Side Sewer System:
No
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
CASCABL906BK