PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
600000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
08/21/2020
Permit Issued Date:
12/28/2020
Inspections Completed Date:
04/01/2022
Permit Remarks:
09/21/2020 RABB CHANGED ADDRESS FROM 2206 TO 2208 44TH AVE SW
CONSTRUCTION VALUATION INFO
Intake Value: New:
445700
Intake Value: Alteration:
0
Total Intake Value:
445700
Issue Value: New:
445700
Issue Value: Alteration:
0
Total Issued Value:
445700
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Existing Building Stories:
1
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
0
PARKING
# of Existing Offsite Parking:
0
# of Proposed Onsite Parking:
2
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
Data Center Building?:
No
Power is Sub-Metered?:
No
SIDE SEWER INFORMATION
Related New Construction Project:
6792013
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Weep Hole
Discharge Point Other Type:
44th Ave SW
Total Disturbed Area:
4600
New Impervious Surface:
632
New Plus Replaced Impervious Surface:
1187
Total Volume Managed by On-Site Stormwater Management (gallons):
17763
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
2
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
ASHLERC982K4