PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
474000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
09/14/2020
Permit Issued Date:
02/11/2021
Inspections Completed Date:
08/23/2022
CONSTRUCTION VALUATION INFO
Intake Value: New:
669531
Intake Value: Alteration:
0
Total Intake Value:
669531
Issue Value: New:
669531
Issue Value: Alteration:
0
Total Issued Value:
669531
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
10-foot curb cut along Sunnyside Ave N, 5 feet south of north property line
PARKING
# of Existing Onsite Parking:
1
# of Proposed Onsite Parking:
2
# of Proposed Offsite Parking:
1
Offsite Parking Location:
Adjacent site to the west, offsite parking agreement provided
# of Proposed Bicycle Parking Spots:
5
Tenant Relocation Assistance
Residential Unit Occupancy:
Vacant Land
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Data Center Building?:
No
Power is Sub-Metered?:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
3275
New Impervious Surface:
942
New Plus Replaced Impervious Surface:
2739
Total Volume Managed by On-Site Stormwater Management (gallons):
22400
Total Area Requiring Soil Amendment:
536
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Dwelling Units:
3
Reuse Existing Side Sewer System:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
COOMBDL846NT