PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
10374030
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
09/22/2021
Permit Issued Date:
02/02/2023
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
13497337
Intake Value: Alteration:
0
Total Intake Value:
13497337
Issue Value: New:
13497337
Issue Value: Alteration:
0
Total Issued Value:
13497337
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC
Action Type:
New
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
6
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Main Existing Use of Building:
Factory and Industrial
Existing Occupancy:
F-2 Factory - Low Hazard
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
Will request a curb cut for trash and recycle only.
PARKING
# of Existing Onsite Parking:
15
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
171
Tenant Relocation Assistance
Residential Unit Occupancy:
All Residential Units Occupied by Property Owner
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
No
Stairway Pressurization:
Yes
Smoke Removal System:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
Mechanical System Scope:
M sheets: 151-177 planset cycle3 dated 8-23-2022
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Commercial
Compliance Path:
Total Building Performance (TBP)
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Resistance
Heating Fuel Type Proposed: Non-Residential:
Electric Heat Pump
Special Requirements:
Residential unit electrical heat using exception (less than 750 w)
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Drainage New/Replaced/Repair Pumps:
1
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
18041
New Impervious Surface:
4309
New Plus Replaced Impervious Surface:
15102
Total Volume Managed by On-Site Stormwater Management (gallons):
90012
Total Area Requiring Soil Amendment:
2939
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
3
Number of New Connections to the Side Sewer:
1
Reuse Existing Side Sewer System:
Yes
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes