PERMIT APPLICATION COMMON
Where on your property are you working?:
Northwest Corner
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
200000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
08/12/2020
Permit Issued Date:
12/31/2020
Inspections Completed Date:
09/13/2021
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
200000
Intake Value: Alteration:
0
Total Intake Value:
200000
Issue Value: New:
199000
Issue Value: Alteration:
1000
Total Issued Value:
200000
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
Add/Alt
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Data Center Building?:
No
Power is Sub-Metered?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes