PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Commercial
Project Value:
50000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
06/16/2020
Permit Issued Date:
12/12/2022
Inspections Completed Date:
09/16/2024
Certificate of Occupancy Issued Date:
09/16/2024
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
44168697
Intake Value: Alteration:
0
Total Intake Value:
44168697
Issue Value: New:
44168697
Issue Value: Alteration:
0
Total Issued Value:
44168697
Total Revision Value:
0
INTERDEPARTMENTAL COORDINATION
SDOT Concept Approval:
Yes
SDOT Permit Accepted:
Yes
SDOT SIP PM:
Tammy Frederick
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
New
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
9
Number of Proposed Below-Grade Building Stories:
2
Number of Mezzanines:
0
Is this a high-rise?:
Yes
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Proposed Onsite Parking:
116
# of Proposed Offsite Parking:
0
# of Proposed Accessible Parking:
3
# of Proposed Bicycle Parking Spots:
113
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
Yes
Smoke Removal System:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Total Building Performance (TBP)
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Electric Heat Pump
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
25453
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
24933
Total Volume Managed by On-Site Stormwater Management (gallons):
105507
Total Area Requiring Soil Amendment:
520
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
2
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
3
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
0
Reuse Existing Side Sewer System:
Yes