PERMIT APPLICATION COMMON
Where on your property are you working?:
The work will take place strictly within the property limits with no alterations to city right of way. A new shed/utility closet, roofed with a deck, as well as a new front porch will be the only structural changes that change the plan, profile of structure. The proposed AADU will be entirely built beneath the existing floor plan of the structure.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
45000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
07/29/2020
Permit Issued Date:
10/09/2020
CONSTRUCTION VALUATION INFO
Intake Value: New:
299669
Intake Value: Alteration:
0
Total Intake Value:
299669
Issue Value: New:
157466
Issue Value: Alteration:
142203
Total Issued Value:
299669
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
Yes
Are you changing the envelope?:
No
Action Type:
Add/Alt
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
0
# of Proposed Onsite Parking:
0
Offsite Parking Location:
Curb
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Occupied by Property Owner
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
Data Center Building?:
No
Power is Sub-Metered?:
No