PERMIT APPLICATION COMMON
Where on your property are you working?:
Work will be conducted in the southeast portion of the property, within an existing paved parking lot.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Industrial
Project Value:
200000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
08/19/2020
Permit Issued Date:
09/24/2020
Inspections Completed Date:
03/15/2022
Certificate of Occupancy Issued Date:
03/15/2022
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
200000
Total Intake Value:
200000
Issue Value: New:
200000
Issue Value: Alteration:
0
Total Issued Value:
200000
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
New
Number of Existing Building Stories:
1
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
1
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
n/a
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Offsite Parking Location:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes