PERMIT APPLICATION COMMON
Where on your property are you working?:
Entire site
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
10000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
04/19/2022
Permit Remarks:
Do not know permit tracking level
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
9841029
Intake Value: Alteration:
0
Total Intake Value:
9841029
Issue Value: New:
81227683
Issue Value: Alteration:
0
Total Issued Value:
81227683
Total Revision Value:
0
INTERDEPARTMENTAL COORDINATION
SDOT Concept Approval:
Yes
SDOT SIP PM:
Jackson Koch
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
New
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
5
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
Proposed vehicle access off alley
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
36
# of Proposed Offsite Parking:
0
Offsite Parking Location:
N/A
# of Proposed Accessible Parking:
2
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
76
Tenant Relocation Assistance
Residential Unit Occupancy:
Do Not Know-Refer to Property Owner and Tenant Assistance
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
No
Stairway Pressurization:
No
Smoke Removal System:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
Mechanical System Scope:
Do not know mechanical system scope
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Commercial
Compliance Path:
Total Building Performance (TBP)
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
rooftop units for apartment building common areas
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Heating Fuel Type Proposed: Non-Residential:
Electric Heat Pump
Special Requirements:
Solar ready per C411. No onsite renewable energy per exception 2.
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
13765
New Impervious Surface:
11923
New Plus Replaced Impervious Surface:
12981
Total Volume Managed by On-Site Stormwater Management (gallons):
20638
Total Area Requiring Soil Amendment:
784
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Dwelling Units:
1
Reuse Existing Side Sewer System:
No
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
ARSENC*850DO