PERMIT APPLICATION COMMON
Where on your property are you working?:
Northern half of the property which is an existing parking lot.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
22000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
07/16/2020
Permit Issued Date:
10/19/2021
Inspections Completed Date:
02/14/2024
Certificate of Occupancy Issued Date:
02/14/2024
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
10438517
Intake Value: Alteration:
0
Total Intake Value:
10438517
Issue Value: New:
10492156
Issue Value: Alteration:
0
Total Issued Value:
10492156
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
New
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
8
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
34
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Offsite Parking Location:
n/a
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
104
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
No
Smoke Removal System:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Commercial
Compliance Path:
Total Building Performance (TBP)
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
97% eff. hot water heater
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Resistance
Heating Fuel Type Proposed: Non-Residential:
Electric Heat Pump
Special Requirements:
Embodied carbon savings is allowed in C407 on this project only per Duane Jonlin.
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
13205
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
12552
Total Volume Managed by On-Site Stormwater Management (gallons):
66067
Total Area Requiring Soil Amendment:
653
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Dwelling Units:
126
Reuse Existing Side Sewer System:
No
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
SWINEB*992DR