PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
35000000
CONSTRUCTION VALUATION INFO
Intake Value: New:
35000000
Intake Value: Alteration:
0
Total Intake Value:
35000000
Total Issued Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Action Type:
New
Is this a high-rise?:
Yes
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is the ground disturbance in an environmentally critical area?:
No
What is the amount of ground disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
12/17/2018
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
9962
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
9962
Total Volume Managed by On-Site Stormwater Management (gallons):
16321
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
0
Reuse Existing Side Sewer System:
No