PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
500000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
02/24/2020
Permit Issued Date:
06/22/2020
Inspections Completed Date:
07/30/2021
Permit Remarks:
Reuse of existing curb cut on 9th Ave W
CONSTRUCTION VALUATION INFO
Intake Value: New:
561200
Intake Value: Alteration:
0
Total Intake Value:
561200
Issue Value: New:
561200
Issue Value: Alteration:
0
Total Issued Value:
561200
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Existing Building Stories:
1.5
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Basement
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
Reuse of existing curb cut on 9th Ave W
PARKING
# of Proposed Onsite Parking:
1
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Occupied by Property Owner
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
Cooling Fuel Type Proposed: Residential:
Natural Gas
SIDE SEWER INFORMATION
Related New Construction Project:
6755726
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Weep Hole
Discharge Point Other Type:
(9th Ave W)
Total Disturbed Area:
5129
New Impervious Surface:
696
New Plus Replaced Impervious Surface:
1748
Total Volume Managed by On-Site Stormwater Management (gallons):
22748
Total Area Requiring Soil Amendment:
98
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
1
Reuse Existing Side Sewer System:
Yes