PERMIT APPLICATION COMMON
Where on your property are you working?:
West portion of lot
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
200000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
11/22/2019
CONSTRUCTION VALUATION INFO
Intake Value: New:
760336
Intake Value: Alteration:
0
Total Intake Value:
760336
Issue Value: New:
0
Issue Value: Alteration:
0
Total Issued Value:
0
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
No
Action Type:
New
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas