PERMIT APPLICATION COMMON
Where on your property are you working?:
Proposed work will encompass entire site
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
850000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
11/07/2019
Permit Issued Date:
04/15/2020
Inspections Completed Date:
01/21/2021
Permit Remarks:
One new 10' curb cut on NW 64th St
CONSTRUCTION VALUATION INFO
Intake Value: New:
614688
Intake Value: Alteration:
0
Total Intake Value:
614688
Issue Value: New:
614688
Issue Value: Alteration:
0
Total Issued Value:
614688
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
One new 10' curb cut on NW 64th St
PARKING
# of Proposed Onsite Parking:
2
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Natural Gas
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
4987
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
2937
Total Volume Managed by On-Site Stormwater Management (gallons):
45471
Total Area Requiring Soil Amendment:
2050
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
1
Reuse Existing Side Sewer System:
Yes