Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Commercial
Project Value:
50000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
06/23/2020
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
49454709
Intake Value: Alteration:
0
Total Intake Value:
49454709
Issue Value: New:
59356466
Issue Value: Alteration:
0
Total Issued Value:
59356466
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
Yes
Action Type:
New
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
22
Number of Proposed Below-Grade Building Stories:
2
Number of Mezzanines:
0
Is this a high-rise?:
Yes
Will you change the building use or occupancy?:
Yes
Main Existing Use of Building:
Business
Existing Occupancy:
B Bank
Will your application include a new standard plan?:
Yes
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
na
PARKING
# of Existing Onsite Parking:
25
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
2
# of Proposed Onsite Parking:
53
# of Proposed Offsite Parking:
0
Offsite Parking Location:
0
# of Proposed Accessible Parking:
5
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
296
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
Yes
Smoke Removal System:
Yes
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Commercial
Compliance Path:
Total Building Performance (TBP)
Is there a commercial kitchen hood exhaust system?:
Yes
Is there a fume hood?:
Yes
Describe any other mechanical systems to be installed as part of this project.:
Full HVAC +heat pumps
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Heating Fuel Type Proposed: Non-Residential:
Electric Heat Pump
Special Requirements:
SEC C411 exception 2
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
1
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
15604
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
14208
Total Volume Managed by On-Site Stormwater Management (gallons):
79490
Total Area Requiring Soil Amendment:
1396
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
2
Number of New Connections to the Side Sewer:
3
Reuse Existing Side Sewer System:
Yes
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No