PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
03/23/2020
Permit Issued Date:
01/14/2021
Inspections Completed Date:
09/09/2021
Certificate of Occupancy Issued Date:
09/09/2021
CONSTRUCTION VALUATION INFO
Intake Value: New:
3800000
Intake Value: Alteration:
0
Total Intake Value:
3800000
Issue Value: New:
3800000
Issue Value: Alteration:
0
Total Issued Value:
3800000
PERMIT APPLICATION COMMON
Where on your property are you working?:
4/28/20 SAC - Address changed from 3900 Montlake BLVD NE to 3831 Walla Walla RD NE
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Institutional
Project Value:
3800000
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Proposed Onsite Parking:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
New
Number of Proposed Building Stories:
1
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
1
Is this a high-rise?:
No
WASTE DIVERSION
Waste Diversion Plan Required:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any ground-mounted exterior equipment?:
No
Is there any wall-mounted exterior equipment?:
No
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Commercial
Compliance Path:
Component Performance
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Electric Resistance
Cooling Fuel Type Proposed: Non-Residential:
Unknown
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Other
Discharge Point Other Type:
EX ONSITE STORM SS
Total Disturbed Area:
18331
New Impervious Surface:
6000
New Plus Replaced Impervious Surface:
13159
Total Volume Managed by On-Site Stormwater Management (gallons):
6758
Total Area Requiring Soil Amendment:
5172
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Reuse Existing Side Sewer System:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
MAMORC*190N6