PERMIT APPLICATION COMMON
Where on your property are you working?:
private lot
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Commercial
Project Value:
2000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
04/22/2020
Permit Issued Date:
07/21/2022
Inspections Completed Date:
05/31/2024
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
600000
Intake Value: Alteration:
0
Total Intake Value:
600000
Issue Value: New:
600000
Issue Value: Alteration:
0
Total Issued Value:
600000
Total Revision Value:
0
INTERDEPARTMENTAL COORDINATION
SDOT Permit Accepted:
Yes
SDOT SIP PM:
YM
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
New
Number of Proposed Building Stories:
0
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Offsite Parking Location:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
Elevator Pressurization:
No
Stairway Pressurization:
No
Smoke Removal System:
No
Accessible Elevator Egress:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
DRAINAGE INFORMATION
Drainage Type of Work:
Addition/Alteration
Number of New Drainage Connections to the Main:
1
Discharge Point:
Storm System
SANITARY INFORMATION
Sanitary Type of Work:
None
SPECIAL PROGRAMS
Is this project receiving Opportunity Zone Funds?:
No