PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
200000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
08/15/2019
Permit Issued Date:
01/15/2020
Inspections Completed Date:
03/26/2021
Permit Remarks:
9/5/2019 SLB CHANGED ADDRESS FROM 223
TO 219 31ST AVE
CONSTRUCTION VALUATION INFO
Intake Value: New:
612700
Intake Value: Alteration:
0
Total Intake Value:
612700
Issue Value: New:
612700
Issue Value: Alteration:
0
Total Issued Value:
612700
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
10 feet on 31st Ave
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
1
# of Proposed Offsite Parking:
0
Offsite Parking Location:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Weep Hole
Total Disturbed Area:
3953
New Impervious Surface:
2500
New Plus Replaced Impervious Surface:
2755
Total Volume Managed by On-Site Stormwater Management (gallons):
2755
Total Area Requiring Soil Amendment:
953
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
1
Reuse Existing Side Sewer System:
Yes