PERMIT APPLICATION COMMON
Where on your property are you working?:
entire lot
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
1200000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
08/14/2019
Permit Issued Date:
07/27/2020
Inspections Completed Date:
11/22/2021
CONSTRUCTION VALUATION INFO
Intake Value: New:
588534
Intake Value: Alteration:
0
Total Intake Value:
588534
Issue Value: New:
619232
Issue Value: Alteration:
0
Total Issued Value:
619232
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
To permit a 10' curb cut along NE 92nd St, approx. 5' west of east property line
PARKING
# of Proposed Onsite Parking:
6
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
5122
New Impervious Surface:
759
New Plus Replaced Impervious Surface:
4121
Total Volume Managed by On-Site Stormwater Management (gallons):
72402
Total Area Requiring Soil Amendment:
1001
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
6
Reuse Existing Side Sewer System:
Yes