PERMIT APPLICATION COMMON
Where on your property are you working?:
Entire Parcel
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
23000000
PERMIT TRACKING COMMON
Review Level:
Dependent Building
Application Completed Date:
09/09/2021
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units Unoccupied
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is the ground disturbance in an environmentally critical area?:
No
What is the amount of ground disturbance?:
More than 750 square feet
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
5
Fill Depth in Feet (maximum):
0
Foundation Type:
Spread Footing
Does anyone live or work here?:
No
Is the disposal site inside the city?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
MARPACL055JP