PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
06/19/2019
Permit Issued Date:
01/15/2020
Inspections Completed Date:
11/24/2020
CONSTRUCTION VALUATION INFO
Intake Value: New:
200000
Intake Value: Alteration:
0
Total Intake Value:
200000
Issue Value: New:
579887
Issue Value: Alteration:
0
Total Issued Value:
579887
PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
200000
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Proposed Onsite Parking:
3
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Other
Discharge Point Other Type:
"FORMERLY COMBINED"
Total Disturbed Area:
4500
New Impervious Surface:
2514
New Plus Replaced Impervious Surface:
2814
Total Volume Managed by On-Site Stormwater Management (gallons):
27111
Total Area Requiring Soil Amendment:
1686
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
2
Reuse Existing Side Sewer System:
Yes