PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
155341756
CONSTRUCTION VALUATION INFO
Intake Value: New:
155341756
Intake Value: Alteration:
0
Total Intake Value:
155341756
Issue Value: New:
155341756
Issue Value: Alteration:
0
Total Issued Value:
155341756
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
11
Number of Mezzanines:
0
Is this a high-rise?:
Yes
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is the ground disturbance in an environmentally critical area?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
PERMIT TRACKING COMMON
Application Completed Date:
11/04/2019
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
Number of Proposed Onsite Parking Spaces:
371
Number of Proposed Bicycle Parking Spots:
449
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
Yes
Smoke Removal System:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Commercial
Compliance Path:
Target Performance Path (TPP)
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Electric Heat Pump
Cooling Fuel Type Proposed: Non-Residential:
Electric Heat Pump
Special Requirements:
34.3 kbtu/s.f./yr ( 17% saving, Green building DR20-2017 req. 15% saving)
Power is Sub-Metered?:
Yes
SANITARY INFORMATION
Reuse Existing Side Sewer System:
No