PERMIT APPLICATION COMMON
Where on your property are you working?:
entire site
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Commercial
Project Value:
30
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
06/17/2020
Permit Issued Date:
01/02/2022
Inspections Completed Date:
04/25/2024
Permit Remarks:
Prior to final of the demolition permit, a completed building permit must be accepted or all disturbed areas to be compost amended or hard surface to properly drain to the combined sewer and all side sewers to be capped under a side sewer permit.
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is the ground disturbance in an environmentally critical area?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
22
Fill Depth in Feet (maximum):
1
Foundation Type:
Spread Footing
Does anyone live or work here?:
Yes
Is the disposal site inside the city?:
No
DEMOLITION INFO
Type of Demolition:
Demolition
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
WGCLAC*370N0