PERMIT APPLICATION COMMON
Where on your property are you working?:
5/14/2019 SLB CHANGED ADDRESS FROM
1803 TO 1805 20TH AVE
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
600000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
03/18/2019
Permit Issued Date:
01/10/2020
Inspections Completed Date:
10/27/2021
CONSTRUCTION VALUATION INFO
Intake Value: New:
1180331
Intake Value: Alteration:
0
Total Intake Value:
1180331
Issue Value: New:
799354
Issue Value: Alteration:
0
Total Issued Value:
799354
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Is this a substantial alteration?:
No
Are you changing the envelope?:
Yes
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
0
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Offsite Parking Location:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
10
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Weep Hole
Total Disturbed Area:
4810
New Impervious Surface:
2510
New Plus Replaced Impervious Surface:
3940
Total Volume Managed by On-Site Stormwater Management (gallons):
30038
Total Area Requiring Soil Amendment:
870
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
8
Reuse Existing Side Sewer System:
Yes