PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
900000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
04/17/2019
Permit Issued Date:
02/19/2020
Inspections Completed Date:
08/12/2021
CONSTRUCTION VALUATION INFO
Intake Value: New:
695895
Intake Value: Alteration:
0
Total Intake Value:
695895
Issue Value: New:
714146
Issue Value: Alteration:
0
Total Issued Value:
714146
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
More than 1 cubic yard
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
4
Fill Depth in Feet (maximum):
0
Foundation Type:
Spread Footing
Does anyone live or work here?:
Yes
Is the disposal site inside the city?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
1
# of Existing Offsite Parking:
0
# of Proposed Onsite Parking:
2
# of Proposed Offsite Parking:
1
Offsite Parking Location:
2114 9TH AVE W
# of Proposed Bicycle Parking Spots:
3
Tenant Relocation Assistance
Residential Unit Occupancy:
TRAO in process, okay to issue
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
Cooling Fuel Type Proposed: Residential:
Unknown
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Other
Discharge Point Other Type:
FORMERLY COMBINE
Total Disturbed Area:
3783
New Impervious Surface:
1977
New Plus Replaced Impervious Surface:
3035
Total Volume Managed by On-Site Stormwater Management (gallons):
31600
Total Area Requiring Soil Amendment:
748
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
3
Reuse Existing Side Sewer System:
Yes